skip to content link

Who Does What in a Lab Relocation: Roles for Lab Managers, Facilities, EHS, and Design Teams

A lab relocation has five owners. The principal investigator or lab manager owns the science: what moves, which samples matter most, and how long work can stop. Facilities owns the buildings, including access, elevators, loading docks, and utilities. EHS owns safety clearance and the sign-off on the space the lab leaves behind. Architects and engineers own the fit of the new space. The mover owns the physical move and the schedule that connects everyone else's tasks.

Most delays in a lab move happen at the handoffs, where two groups each assume the other has a task covered. This article breaks down what each role owns so you can assign every task before the move starts. If you want the step-by-step sequence instead, our lab relocation checklist for Boston facilities covers the order of work.

Lab Relocation Responsibilities at a Glance

TaskOwnerWorks with 
Equipment, chemical, and sample inventoryPI or lab managerEHS, mover
Sample priorities and downtime tolerancePI or lab managerMover
Instrument service contracts and vendor contactsPI or lab managerManufacturers, mover
Building access, elevators, and loading docksFacilitiesMover
Utility shutdowns and reconnectionsFacilitiesDesign team, vendors
Chemical review and disposal decisionsEHSLab, mover
Biosafety cabinet decontamination and recertificationEHSCertified technician, facilities
Decommissioning sign-off for the vacated spaceEHSLab, facilities
Equipment layout and utility design at the new siteArchitects and engineersLab, mover, vendors
Floor loading and rigging path reviewStructural engineerMover, facilities
Instrument disconnection, reinstallation, and requalificationManufacturer or service vendorLab, mover
Packing, transport, placement, and the move day scheduleMoverAll of the above

What the PI or Lab Manager Owns

The person who runs the science owns every decision about the science. In a university lab, that is the principal investigator, with the lab manager doing much of the planning. In a company, the lab owner may be a research operations lead or a department head. Whoever holds the role should have the authority to make calls without waiting on a committee.

Inventory. The lab builds the master list of equipment, chemicals, and samples. Each list answers a different question for a different group, which our post on lab inventory before a move explains.

Sample priorities. Only the lab knows which samples are irreplaceable, which the lab can regenerate, and which it can discard. Those rankings shape the cold storage plan and decide what moves first.

Downtime tolerance. The lab decides how long each instrument and each line of work can stop. An experiment that cannot pause may justify moving in stages. Our guide to structuring a phased relocation shows how to split a move around active work.

What not to move. Surplus equipment, expired reagents, and old samples cost money to pack and transport. The lab decides what to leave behind, and EHS decides how to dispose of hazardous items.

Vendor relationships. The lab holds the service contracts and warranty terms, so it naturally owns the vendor contact list.

What Facilities Owns

Facilities owns everything about the buildings at both ends of the move. In leased space, the landlord's property management team may control docks, elevators, and move-in rules, so bring them in early.

  • Building access, badges, and approval for after-hours work.
  • Freight elevator reservations and confirmed weight limits.
  • Loading dock time slots at both sites.
  • Floor and wall protection requirements along the move route.
  • Shutdowns for gases, vacuum, purified water, and steam at the origin.
  • Power, gas, water, and exhaust ready and tested at the destination before move day.
  • Disconnecting and reconnecting equipment that ties into building systems, such as ducted biosafety cabinets and autoclaves.

The most common facilities gap is utility readiness at the new site. An instrument that arrives on schedule but finds the wrong outlet or no gas supply sits idle until the trades come back.

What EHS Owns

EHS owns the safety clearances that let the move start and the sign-offs that let work resume.

Chemicals. EHS reviews the chemical inventory, decides what to dispose of, and approves how the rest travels. Laboratory chemicals move under DOT hazardous materials rules, and our post on hazmat transport for laboratory chemicals covers what that involves.

Biological materials and equipment. EHS or the biosafety officer schedules decontamination and recertification of biosafety cabinets and updates any registrations that list the lab's location. If the lab uses radioactive materials, the radiation safety officer handles license changes for the new space.

Decommissioning. EHS signs off that the vacated space is clear of chemical, biological, and radiological hazards. That closeout is a documented process, not a cleanup, as our post on decommissioning and Massachusetts regulatory standards explains.

Readiness of the new space. EHS confirms that safety equipment such as eyewash stations, showers, and fume hoods is in place and working before hazardous work begins.

What Architects and Engineers Need From the Move Team

Architects and engineers design the new space around the equipment, so they need equipment data early. From the lab and the mover, the design team needs:

  • An equipment list with dimensions, weights, and utility requirements for each item.
  • Heat loads and vibration sensitivity for instruments that have them.
  • The location plan for every piece of equipment, by room and bench.
  • The rigging path for the heaviest items, so a structural engineer can check floor loading along the route and at the final location.
  • Which equipment is moving and which is new, since new equipment may arrive on a different schedule.

In return, the mover needs drawings with equipment locations, room numbers, door and corridor dimensions, elevator specifications, and floor load limits. Our post on coordinating your lab move with fit-out and design-build covers this exchange in detail.

What the Mover Owns

The mover owns the physical move and the schedule that ties every other role together.

  • Walkthroughs at both sites to confirm access, routes, and equipment handling needs.
  • A move plan that sequences equipment around vendor visits, certifications, and sample storage.
  • Packing methods and materials for each type of equipment.
  • A labeling system that maps every item to its room and bench at the destination.
  • Building protection along the route.
  • Transport, placement, and leveling according to the new floor plan.
  • Interim storage when the new space is not ready.

The mover does not own EHS approvals, utility work, or instrument certification. A good mover tracks those items on the schedule anyway, because a missing sign-off stops the move as surely as a missing truck. Lab Movers works with each of these groups on laboratory moves across Boston and the surrounding region.

Where Handoffs Break Down

Most problems in a lab move trace back to a task that sat between two owners. Watch for these gaps:

  • Power at the destination was never tested against the equipment list.
  • The biosafety cabinet certifier was not booked until after the move date.
  • Someone reserved the freight elevator but not the loading dock.
  • A vendor engineer arrived before utilities were live.
  • Nobody decided where samples would live while the freezers were off.
  • The lab had no single person with authority to make decisions on move day.

The fix is simple to describe and takes discipline to run. Name one lead for each role, put every task in the table above against a name, and review the open items together on a regular schedule until the last instrument is back in service.

Topics:
Call Icon